[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983311":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},983311,714,1,"单选题","某工程建设项目的资格预审文件根据《标准施工招标资格预审文件》（2007年版）编制，采用有限数量制评审。资格预审文件规定通过资格预审的申请人数量为7家，实际通过详细审查的申请人为3家。对此，下列做法中正确的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","重新组织资格预审",false,{"key":16,"text":17,"correct":14},"B","修改资格预审标准，重新评审",{"key":19,"text":20,"correct":21},"C","3家均通过资格预审，不再进行评分",true,{"key":23,"text":24,"correct":14},"D","以资格后审方式招标","评审采用有限数量制的，通过详细审查的申请人超过3个但没有超过资格预审文件规定数量(N)的，不再进行评分，均通过资格预审；通过详细审查的申请人数量超过资格预审文件规定数量(N)的，资格审查委员会应按资格预审文件规定的评审因素和评分标准进行评审，并依据规定的评分标准进行评分，按得分由高到低的顺序进行排序，确定资格预审文件规定数量(N)的申请人通过资格预审。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购专业实务","建筑工程",0]