[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983283":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},983283,714,1,"单选题","工程承包方式主要有()方式。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","分包与总包",false,{"key":16,"text":17,"correct":14},"B","专业分包与劳务分包",{"key":19,"text":20,"correct":14},"C","施工承包与设计承包",{"key":22,"text":23,"correct":24},"D","施工承包和设计一施工一体化承包",true,"工程承包方式主要有施工承包方式和设计一施工一体化承包方式两类。其中，施工承包方式下，工程设计和施工分离，分别由不同主体负责实施，工程承包人按照招标人提供的设计图纸和技术规范施工。而按照设计一施工一体化工程承包方式要求，工程承包人应该根据招标人的要求同时负责工程设计和施工。设计施工一体化工程承包方式与施工承包方式的最大区别是招标人不再提供工程设计图纸，只提供基本的工程方案（初步）设计\u002F工艺方案设计作为招标条件，而将此后的工程设计与施工责任及相应风险转移给一个总承包人。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购专业实务","建筑工程",0]