[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983268":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},983268,714,1,"单选题","某铁路工程建设项目，由于前期拆迁拖延，延误了建设工期。在满足其他条件的情况下，为缩短工期，招标人可以采取的措施是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","适当增加工程施工招标标段的数量",true,{"key":16,"text":17,"correct":18},"B","同时组织初步设计招标和施工招标",false,{"key":20,"text":21,"correct":18},"C","安排具备资质的承包人进场施工，同时办理招标手续",{"key":23,"text":24,"correct":18},"D","先发出招标文件，在开标前一周内补充设计技术参数","工程总工期及其进度计划对合同标段划分会产生很大的影响。标段规模小，标段数量多，进场施工的承包人多，容易集中各承包人加快投入更多的资源力量，在多个工点齐头并进赶工期，但需要项目发包人具有相应的管理力量配合以及充足、及时的资金保障。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购专业实务","建筑工程",0]