[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983267":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},983267,714,1,"单选题","确定工程货物招标顺序的主要因素不包括()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程建设项目进度要求或项目业主对货物的实际需求时间",false,{"key":16,"text":17,"correct":14},"B","货物的生产和供应周期",{"key":19,"text":20,"correct":21},"C","货物的数量需求",true,{"key":23,"text":24,"correct":14},"D","完成招标程序所需要的时间","确定工程货物招标顺序的主要因素包括：①工程建设项目进度要求或项目业主对货物的实际需求时间；②货物的生产和供应周期；③完成招标程序所需要的时间；④工程设计、施工条件与货物技术参数确定之间的相互制约关系；⑤货物不同的功能用途以及施工安装的先后顺序。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购专业实务","建筑工程",0]