[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983264":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},983264,714,1,"单选题","与发包人采购相比，由承包人采购工程材料设备具有()的特点。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","便于实现采购和工程的系统化管理",true,{"key":16,"text":17,"correct":18},"B","采购和结算操作管理相对复杂",false,{"key":20,"text":21,"correct":18},"C","仅适合简单的工程",{"key":23,"text":24,"correct":18},"D","适合于材料设备技术相对复杂的工程","在工程承包方式中，工程设备材料通常有三种采购供应方式：一是招标人采购，二是承包人采购，三是招标人与承包人联合采购。对于承包人投标报价范围内已经包括且由承包人自主定价的设备材料，属于承包人采购的内容。这种方式与招标人自行采购供货方式的利弊正好相反，责任风险均由承包人承担，采购和结算操作管理简单。这种方式比较适用于工期比较短、规模较小或材料设备技术规格简单的工程。工期较长的大型工程，如由承包人采购材料设备，宜在合同条款中设置相应材料设备的价格调整条款，以减少价格波动给承包人带来的过多风险。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购专业实务","建筑工程",0]