[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983263":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},983263,714,1,"单选题","工程建设项目中某些大宗的、重要的、新型特殊设备材料适用()方式。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","承包人采购",false,{"key":16,"text":17,"correct":14},"B","招标人与承包人联合采购",{"key":19,"text":20,"correct":21},"C","招标人采购",true,{"key":23,"text":24,"correct":14},"D","招标人自行制造","招标人为了控制工程建设项目中某些大宗的、重要的、新型特殊设备材料的质量和价格，通常采取自行采购供货的方式，与供货商签订供货合同，供货商按照承包人提出并经招标人审核批准的供货计划定期供货。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购专业实务","建筑工程",0]