[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983262":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},983262,714,1,"单选题","按照工程项目建设程序，下列投资控制目标排列顺序正确的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","投资估算、设计概算、施工图预算、竣工决算、合同价格",false,{"key":16,"text":17,"correct":14},"B","设计概算、投资估算、施工图预算、竣工决算、中标价格",{"key":19,"text":20,"correct":21},"C","投资估算、设计概算、施工图预算、合同价格、竣工决算",true,{"key":23,"text":24,"correct":14},"D","设计概算、投资估算、施工图预算、合同价格、竣工决算","工程造价控制目标和形式与工程建设程序密切相关。工程建设的不同阶段具有各自的造价控制目标和形式。一般按建设程序划分为四种目标形式：工程可行性研究阶段的投资估算、初步设计阶段的设计概算、施工图设计阶段的施工图预算、竣工验收阶段的竣工结算。工程造价控制次序是：投资估算控制设计概算，设计概算控制施工图预算，施工图预算控制竣工结算。设计概算是工程造价控制的第一个关键阶段；工程施工招标形成工程签约合同价（中标价），是工程造价控制的第二个重要阶段。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购专业实务","建筑工程",0]