[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983261":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},983261,714,1,"单选题","某商场工程建设项目招标，比较合理的招标顺序是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","①扶梯及电梯采购、②工程施工、③工程设计、④灯具采购",false,{"key":16,"text":17,"correct":14},"B","①工程施工、②工程设计、③扶梯及电梯采购、④灯具采购",{"key":19,"text":20,"correct":21},"C","①工程设计、②扶梯及电梯采购、③工程施工、④灯具采购",true,{"key":23,"text":24,"correct":14},"D","①工程设计、②灯具采购、③工程施工、④扶梯及电梯采购","根据工程施工总体进度顺序确定工程招标顺序，一般是：①施工准备工程在前，主体工程在后；②制约工期关键线路的工程在前，施工时间比较短的工程在后；③土建工程在前，设备安装在后；④结构工程在前，装饰工程在后；⑤制约后续的工程在前，紧前的工程在后；⑥工程施工在前，工程货物采购在后，但部分主要设备采购应在工程施工之前招标，以便据此确定工程设计或施工的技术参数。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购专业实务","建筑工程",0]