[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983257":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},983257,714,1,"单选题","交通、铁道、石油化工、水利等工程建设项目在完成初步设计报告后组织招标，其工程造价控制目标一般以()为限额。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程初步设计概算",true,{"key":16,"text":17,"correct":18},"B","招标工程相应范围编制的执行概算",false,{"key":20,"text":21,"correct":18},"C","施工图预算",{"key":23,"text":24,"correct":18},"D","工程设计概算","交通、铁道、石油化工、水利等工程建设项目在完成初步设计报告后组织招标，其工程造价控制目标一般以工程初步设计概算为限额；水电工程在完成招标设计后组织招标，其工程造价控制目标一般以依据招标工程相应范围编制的执行概算为限额；房屋建筑和市政工程在施工图完成后组织施工招标，其工程造价控制目标一般以施工图预算为限额。政府审批的工程项目，如招标后的签约价超过工程初步设计概算限额，应当申请调整工程初步设计概算额。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购专业实务","建筑工程",0]