[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983228":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983228,712,2,"多选题","影响工程咨询服务项目进度的常见因素有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","可预见事件",false,{"key":16,"text":17,"correct":18},"B","项目状态信息",true,{"key":20,"text":21,"correct":18},"C","计划变更调整",{"key":23,"text":24,"correct":18},"D","项目参与者的行为",{"key":26,"text":27,"correct":18},"E","工程咨询服务项目实现的条件","BCDE","工程咨询服务项目影响进度的因素很多，如人为因素、技术因素、资金因素、环境因素等，其中入为因素是最重要的因素，技术因素归根到底也是人的因素，影响工程咨询服务项目进度的常见因素包括：①工程咨询服务项目实现的条件；②项目参与者的行为；③不可预见事件；④项目状态信息；⑤计划变更调整。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]