[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983217":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983217,712,2,"多选题","项目可行性研究报告中，贯彻宏观调控政策综合评价的二级指标有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","对经济规模论证情况",true,{"key":16,"text":17,"correct":14},"B","对合理布局论证情况",{"key":19,"text":20,"correct":21},"C","财务、金融风险分析情况",false,{"key":23,"text":24,"correct":14},"D","对提高技术水平论证情况",{"key":26,"text":27,"correct":21},"E","政策风险分析情况","ABD","贯彻宏观调控政策综合评价的二级指标有：①对建设项目的必要性及利用现有基础可能性；②对经济规模论证情况；③对优化结构的论证情况；④对提高技术水平论证情况；⑤对合理布局论证情况。CE两项属于风险分析情况综合评价的二级指标。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]