[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983204":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983204,712,2,"多选题","企业生产进度控制的内容主要包括()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","准备进度控制",false,{"key":16,"text":17,"correct":18},"B","工序进度控制",true,{"key":20,"text":21,"correct":14},"C","设计进度控制",{"key":23,"text":24,"correct":18},"D","投入进度控制",{"key":26,"text":27,"correct":18},"E","产出进度控制","BDE","企业生产进度控制的内容主要包括：①投入进度控制，指对工艺装备、原材料、毛坯、零部件投入提前期的控制；②工序进度控制，指对零部件和产品在加工过程中每道工序的进度控制；③产出进度控制，包括对最终产品完成制造的日期、生产数量的控制，对产品部件的配套控制和品种组合均衡性的控制。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]