[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983198":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983198,712,2,"多选题","物流服务项目范围变更控制的依据有()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","物流服务项目工作分解结构",true,{"key":16,"text":17,"correct":14},"B","物流服务项目范围管理计划",{"key":19,"text":20,"correct":14},"C","物流服务项目范围变更的请求",{"key":22,"text":23,"correct":24},"D","物流服务项目范围综述",false,{"key":26,"text":27,"correct":14},"E","物流服务项目的实施情况报告","ABCE","物流服务项目范围变更控制的依据主要包括四个方面的文件或信息：①物流服务项目工作分解结构；②物流服务项目的实施情况报告；③物流服务项目范围变更的请求；④物流服务项目范围管理计划。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]