[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983191":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983191,712,2,"多选题","下列各项属于服务项目成本计划要明确的内容的有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","服务项目总金额",true,{"key":16,"text":17,"correct":14},"B","不可预见费用",{"key":19,"text":20,"correct":21},"C","进度预算明细",false,{"key":23,"text":24,"correct":14},"D","可报销费用的预算明细",{"key":26,"text":27,"correct":14},"E","咨询人员酬金的预算明细","ABDE","服务项目成本计划要明确以下内容：①服务项目总金额，通常包括：人员的酬金、可报销费用和不可预见费用；②咨询人员酬金的预算明细；③可报销费用的预算明细；④不可预见费用。另外，成本计划还需要对支付程序和支付方式做出规定。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]