[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983180":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983180,712,2,"多选题","投融资服务项目进度管理包含的内容有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","投融资服务项目本身必须如期完成，不能耽误项目建设的进度",true,{"key":16,"text":17,"correct":14},"B","资金的融通必须及时、足额，能够全面满足对于投资进度的需求",{"key":19,"text":20,"correct":21},"C","采取系统的控制措施，及时纠正进度偏差",false,{"key":23,"text":24,"correct":21},"D","在制定工作计划时，详细分析可能导致拖延的原因",{"key":26,"text":27,"correct":21},"E","尽可能满足业主的要求","AB","投融资服务项目很大程度上是为整体项目服务的，其往往是一个大型项目的子项目。项目资金的融通计划往往是与项目的进度日期直接相关的。通过对投融资服务项目进度的有效控制，满足预期的工程建设项目进度要求，是投融资项目进度管理的中心任务。投融资服务项目的进度管理包含两方面内容：①投融资服务项目本身必须如期完成，不能耽误项目建设的进度；②融资服务工作的成果，即资金的融通必须及时、足额，能够全面满足对于投资进度的需求。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]