[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983156":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983156,712,2,"多选题","施工阶段项目执行管理层次的主要工作有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","项目稽查",false,{"key":16,"text":17,"correct":18},"B","合同管理",true,{"key":20,"text":21,"correct":18},"C","施工管理",{"key":23,"text":24,"correct":14},"D","项目监测评价",{"key":26,"text":27,"correct":18},"E","资金使用管理","BCE","施工阶段项目执行管理层次的主要工作有：①合同管理；②施工管理；③资金使用管理。A项是项目决策管理在施工阶段的主要工作；D项是项目执行管理在施工阶段的咨询业务。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]