[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983133":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983133,712,2,"多选题","作为货物的质量检验，验收的方式包括()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","采购方单方面验收",true,{"key":16,"text":17,"correct":18},"B","供应方单方面验收",false,{"key":20,"text":21,"correct":14},"C","供需双方共同验收",{"key":23,"text":24,"correct":18},"D","中间商验收",{"key":26,"text":27,"correct":14},"E","第三方验收","ACE","采购方对于重大设备的质量是相当重视和谨慎的，而货物制造企业对于大型项目的风险控制力度很强。综合两方需求，一般会在合同中约定“交货时支付部分货款、产品质量验收之后付清全部款项。”验收的方式主要有：①采购方单方面验收；②供需双方共同验收；③委托第三方验收。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]