[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983132":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983132,712,2,"多选题","关于企业的生产能力及生产能力计划，下列说法错误的有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","生产能力是反映企业现有加工能力的技术参数，反映企业可能的最大生产规模",false,{"key":16,"text":17,"correct":14},"B","生产能力计划分为长期计划和短期计划",{"key":19,"text":20,"correct":21},"C","长期生产能力计划的时间跨度在3年以上",true,{"key":23,"text":24,"correct":21},"D","长期生产能力计划主要的内容是调节生产能力与生产计划数量之间的平衡",{"key":26,"text":27,"correct":14},"E","市场需求不足时，应通过调整生产能力计划，缩小生产规模，减少供给，避免生产能力过剩","CD","C项，长期生产能力计划的时间跨度在2年以上；D项，短期生产能力计划主要的内容是调节生产能力与生产计划数量之间的平衡。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]