[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983113":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983113,712,2,"多选题","物流服务项目范围变更控制的结果有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","生成变更的行动方案",true,{"key":16,"text":17,"correct":14},"B","改善物流服务工作绩效和结果",{"key":19,"text":20,"correct":21},"C","变更物流服务项目范围计划",false,{"key":23,"text":24,"correct":14},"D","生成物流服务范围变更的正式记录",{"key":26,"text":27,"correct":14},"E","生成物流服务项目的范围、工期、成本、质量更新的计划文件","ABDE","物流服务项目范围变更管理与控制的结果有两个：①改善物流服务项目的工作绩效和结果；②生成一系列物流服务项目范围变更控制文件。这些文件包括：①物流服务范围变更的正式记录；②物流服务项目的范围、工期、成本、质量更新的计划文件；③变更的行动方案等。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]