[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983107":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983107,712,2,"多选题","工程建设项目风险管理中广泛使用的风险转移方式有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工程担保",true,{"key":16,"text":17,"correct":14},"B","工程保险",{"key":19,"text":20,"correct":21},"C","建立风险事件应急预案",false,{"key":23,"text":24,"correct":21},"D","制定风险管理制度",{"key":26,"text":27,"correct":14},"E","设定保护性合同条款","ABE","工程建设项目风险管理广泛使用的风险转移方式有：①设定保护性合同条款。在三种转移途径中，利用合同的保护性条款来降低或规避某些风险的转移成本相对较低。②工程担保。工程担保是将风险转移给第三方的途径。③工程保险。工程保险是借助第三方来转移风险，同其他风险方式相比，工程保险转移风险的效率是比较高的。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]