[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983099":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983099,712,2,"多选题","在编制进度总控制计划时，主要遵循()步骤进行。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","由业主或管理咨询单位编制项目进度总控制计划的初始版本",true,{"key":16,"text":17,"correct":18},"B","由设计单位编制项目进度总控制计划的初始版本",false,{"key":20,"text":21,"correct":18},"C","由施工单位编制项目进度总控制计划的初始版本",{"key":23,"text":24,"correct":14},"D","项目进度总控制计划的正式版本",{"key":26,"text":27,"correct":14},"E","项目进度总控制计划的调改版本","ADE","项目进度总控制计划一般由业主或其委托的项目管理咨询单位编制初稿，经项目主要参与方共同讨论确认。进度总控制计划的编制可按以下三个步骤进行：①由业主或管理咨询单位编制项目进度总控制计划的初始版本；②项目进度总控制计划的正式版本；③项目进度总控制计划的调改版本。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]