[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983098":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983098,712,2,"多选题","关于环境影响评价与工程建设程序的对应关系，下列说法正确的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","运行一进行项目周边环境监测",true,{"key":16,"text":17,"correct":18},"B","施工一监督设计，落实评价结论",false,{"key":20,"text":21,"correct":14},"C","项目建议书批准一编制环境影响评价大纲",{"key":23,"text":24,"correct":18},"D","编制工程项目的可行性研究一编制环境影响评价大纲",{"key":26,"text":27,"correct":14},"E","工程设计一监督设计，落实评价结论","ACE","尽管环境影响评价与可行性研究分别进行，但作为建设项目决策的主要依据之一，它应该与工程项目的可行性研究同时完成，表3-2说明了环境影响评价与工程建设程序的这一匹配关系。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]