[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983096":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983096,712,2,"多选题","下列关于施工环境管理要求的表述，正确的有()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","收集和落实施工项目相关的法律法规要求，及时进行合规性评价",true,{"key":16,"text":17,"correct":14},"B","应明确施工项目运行的控制对象",{"key":19,"text":20,"correct":14},"C","环境绩效监测（检查）和改进",{"key":22,"text":23,"correct":24},"D","不影响周边道路的交通秩序",false,{"key":26,"text":27,"correct":14},"E","从制度上规定施工现场实施适宜的运行程序和方法","ABCE","施工环境管理的要求有：①在识别和评价环境因素的基础上确定重要环境因素，明确施工项目运行的控制对象；②收集和落实施工项目相关的法律法规要求，及时进行合规性评价；③结合施工要求，从制度上规定施工现场实施适宜的运行程序和方法；④施工现场应识别可能的紧急情况，制定应急响应措施，提供应急准备手段和资源；⑤环境绩效监测（检查）和改进。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]