[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983095":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983095,712,2,"多选题","在工程建设项目的工程设计与计划阶段，业主的工作内容有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","组织方案设计评审",false,{"key":16,"text":17,"correct":18},"B","审查初步设计概算",true,{"key":20,"text":21,"correct":14},"C","拟定施工合同条款",{"key":23,"text":24,"correct":18},"D","签署施工监理委托合同",{"key":26,"text":27,"correct":14},"E","编制施工组织设计","BD","项目工程设计与计划阶段业主的管理工作内容有：①技术设计工作安排；②设计进度与计划管理；③工程设计质量管理；④编制项目管理组织计划（合同网络图）；⑤编制项目进度总控制计划（初始文本）；⑥编制项目投资\u002F成本总控制计划；⑦编制项目管理实施方案；⑧进行项目的筹融资安排；⑨办理项目的各类政府审批手续；⑩进行施工承包与监理的招标，包括签署施工监理委托合同。AE两项属于项目设计准与审定决策阶段业主的管理工作内容。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]