[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983093":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983093,712,2,"多选题","承包人根据办理的竣工结算文件，向发包人提交竣工结算款的支付申请，该申请应包括()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","竣工结算合同价款总额",true,{"key":16,"text":17,"correct":14},"B","累计已实际支付的合同价款",{"key":19,"text":20,"correct":14},"C","应扣留的质量保证金",{"key":22,"text":23,"correct":24},"D","质量保证金",false,{"key":26,"text":27,"correct":14},"E","实际应支付的竣工结算额金额","ABCE","承包人根据办理的竣工结算文件，向发包人提交竣工结算款的支付申请，该申请应包括：①竣工结算合同价款总额；②累计已实际支付的合同价款；③应扣留的质量保证金；④实际应支付的竣工结算额金额。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]