[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983092":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983092,712,2,"多选题","关于项目进度计划，下列说法正确的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","项目业主与管理咨询单位的周计划与月计划是对应的，包括内容与时限都是对应的，周计划是月计划的细化，是服从和服务于月计划的",true,{"key":16,"text":17,"correct":18},"B","专项管理工作进度计划是跨越周度的计划",false,{"key":20,"text":21,"correct":14},"C","在项目施工期，业主与管理咨询单位的月计划、周计划与项目进度总控计划（一级计划）对应",{"key":23,"text":24,"correct":14},"D","一个完善的进度计划管理体系能使体系内的各个计划在总体与重要的时间节点上完全相互呼应，不但包括两个计划体系之间的呼应，也包括各级计划之间的呼应",{"key":26,"text":27,"correct":14},"E","三级计划一般由总承包方的专业计划工程师运用必要管理软件按短周期滚动编制","ACDE","B项，专项管理工作进度计划是跨越月度的计划，分解开来与项目业主与管理咨询单位的周计划与月计划也是对应和匹配的，只是仅限一个专项工作而特别编制的计划。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]