[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983077":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983077,712,2,"多选题","施工过程的管理活动包括()等阶段。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","施工准备",true,{"key":16,"text":17,"correct":14},"B","施工",{"key":19,"text":20,"correct":21},"C","验收策划",false,{"key":23,"text":24,"correct":14},"D","竣工验收",{"key":26,"text":27,"correct":21},"E","工程移交","ABD","从施工项目的寿命周期来看，施工过程的管理活动依次可分为施工准备、施工、竣工验收等阶段的管理活动。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]