[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983075":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983075,712,2,"多选题","下列各项中，承包人可提出工程索赔的有()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","发包人指令承包人缩短工期导致的额外开支",true,{"key":16,"text":17,"correct":14},"B","发包人要求修改设计造成工期延长",{"key":19,"text":20,"correct":14},"C","不可预见的地下障碍物导致工程返工",{"key":22,"text":23,"correct":24},"D","合同非正常终止",false,{"key":26,"text":27,"correct":14},"E","施工期间，工程材料物价上涨","ABCE","D项，由于发包人违约或发生不可抗力事件等原因造成合同非正常终止，承包人因其遭受经济损失而提出索赔。如果由于承包人的原因导致合同非正常终止，或者合同无法继续履行，发包人可以就此提出索赔。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]