[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983072":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983072,712,2,"多选题","检验批、分部分项工程完成后，其验收单位包括()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","工程监理单位",true,{"key":16,"text":17,"correct":14},"B","建设单位",{"key":19,"text":20,"correct":14},"C","设计单位",{"key":22,"text":23,"correct":24},"D","政府部门",false,{"key":26,"text":27,"correct":24},"E","勘察单位","ABC","检验批、分部分项工程完成，施工单位自行验收合格后，通知建设单位（或工程监理单位）验收，重要的分部分项工程应请设计单位参加验收。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]