[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983069":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983069,712,2,"多选题","空负载试车的一般步骤包括()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","办理各项竣工交接手续",false,{"key":16,"text":17,"correct":18},"B","审查各项准备工作是否已满足试车的需要",true,{"key":20,"text":21,"correct":18},"C","完成启动前的检查、检验、检测，证明可安全运转",{"key":23,"text":24,"correct":18},"D","单机空负荷试运转，确认合格后，即可签单机试运转合格证书",{"key":26,"text":27,"correct":18},"E","空负荷联动试车","BCDE","空负载试车的一般步骤如下：①审阅试车与竣工文件；②审查各项准备工作是否已满足试车的需要；③完成启动前的检查、检验、检测，证明可安全运转；④单机空负荷试运转，确认合格后，即可签单机试运转合格证书；⑤空负荷联动试车。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]