[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983067":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983067,712,2,"多选题","工程建设项目竣工阶段的风险应对措施主要为()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","实施质量验收监控",true,{"key":16,"text":17,"correct":18},"B","将工程价款支付到合同预定的要用户和账户",false,{"key":20,"text":21,"correct":14},"C","工程质量风险转移",{"key":23,"text":24,"correct":18},"D","要求承包商投保工程质量险",{"key":26,"text":27,"correct":18},"E","有效预测风险前景","AC","竣工验收阶段的风险应对措施为：①实施质量验收监控；②工程质量风险转移。B项属于款项支付方面风险的应对措施；D项属于质量风险的应对措施；E项属于政治和社会风险的应对措施。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]