[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983060":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983060,712,2,"多选题","项目主要参与方共同编制并执行的多级进度计划体系包括()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","项目进度总控制计划",true,{"key":16,"text":17,"correct":14},"B","各专业工程进度计划",{"key":19,"text":20,"correct":21},"C","各单项工程进度计划",false,{"key":23,"text":24,"correct":21},"D","项目长周期工程综合进度计划",{"key":26,"text":27,"correct":14},"E","项目短周期工程综合进度计划","ABE","项目主要参与方共同编制并执行的多级进度计划体系由不少于三个层级的计划构成：①第一级计划，即项目进度总控制计划；②第二级计划，即各专业工程进度计划；③第三级计划，即项目短周期工程综合进度计划。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]