[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983059":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983059,712,2,"多选题","竣工验收资料管理从()方面为承包商带来风险。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","由于施工项目经理部或企业未按有关资料管理的规定做，使竣工资料不全或混乱",true,{"key":16,"text":17,"correct":14},"B","监理人未能按规定及时签发相关资料，以致在竣工验收时发生纠纷",{"key":19,"text":20,"correct":14},"C","资源供应方为了今后索取款项故意不按时交付有关证明文件",{"key":22,"text":23,"correct":14},"D","由于市场的供求机制不健全，法规不健全，发包人拖欠工程款，承包人拖欠材料款",{"key":25,"text":26,"correct":27},"E","洪水、地震等不可抗拒自然条件，复杂地质，施工对环境的影响",false,"ABCD","竣工验收资料管理从以下几个方面为承包商带来风险：①由于施工项目经理部或企业未按有关资料管理的规定做，使竣工资料不全或混乱，影响施工项目竣工验收；②发包人与承包人在签订施工承包合同时，对施工技术资料的编制责任和移交期限等事项未能做出全面、完整、明确的规定，造成竣工验收时资料不符合竣工验收规定，影响竣工验收；③监理人未能按规定及时签发相关资料，以致在竣工验收时发生纠纷，影响竣工验收工作的顺利进行；④由于市场的供求机制不健全，法规不健全，发包人拖欠工程款，承包人拖欠材料款、机械设备租赁费，资源供应方为了今后索取款项故意不按时交付有关证明文件，致使竣工验收工作不能正常进行。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]