[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983058":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983058,712,2,"多选题","技术协调应从施工过程管理的组织结构、制约机制、协调程序等方面着手，采取的措施主要有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","建立科学的项目管理内、外部结构",true,{"key":16,"text":17,"correct":14},"B","建立高效合理的项目管理机制",{"key":19,"text":20,"correct":21},"C","整理并保管各类工程技术资料",false,{"key":23,"text":24,"correct":14},"D","建立技术及信息的协调管理程序",{"key":26,"text":27,"correct":14},"E","建立快捷的信息管理枢纽","ABDE","技术协调应从施工过程管理的组织结构、制约机制、协调程序等方面着手，采取以下措施：①建立科学的项目管理内、外部结构；②建立高效合理的项目管理机制；③建立技术及信息的协调管理程序；④建立快捷的信息管理枢纽；⑤制订完善的技术保证措施。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]