[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983057":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983057,712,2,"多选题","在项目设计阶段经常出现的问题主要有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","图纸的可施工性差",true,{"key":16,"text":17,"correct":18},"B","设计深度不能达到规定的标准",false,{"key":20,"text":21,"correct":14},"C","采用材料设备的可获得性差",{"key":23,"text":24,"correct":18},"D","新施工工法的经济性差",{"key":26,"text":27,"correct":18},"E","设计费用支付不及时","AC","在项目设计阶段经常出现的问题主要有：①图纸的可施工性差；②采用材料设备的可获得性差；③新施工工法的可运用性差。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]