[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983056":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983056,712,2,"多选题","设计任务采购过程中，确定中标人的方式主要有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","以方案优劣评价因素为主",true,{"key":16,"text":17,"correct":14},"B","以设计承诺为主决定中标",{"key":19,"text":20,"correct":21},"C","以设计方案价格因素为主",false,{"key":23,"text":24,"correct":21},"D","以设计方案可操作性为主",{"key":26,"text":27,"correct":21},"E","以设计单位规模大小为主","AB","招标方式下，确定中标入主要有以下两种方法：①以方案优劣评价因素为主，一般用于方案设计的招标。②以设计承诺为主决定中标，一般适用于工程设计单位的招标。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]