[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983052":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983052,712,2,"多选题","施工质量控制包括施工准备、施工过程、施工验收等过程的质量控制。下列工程中，属于施工过程质量控制的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工组织设计审核",false,{"key":16,"text":17,"correct":18},"B","质量控制点设置",true,{"key":20,"text":21,"correct":18},"C","工程变更控制",{"key":23,"text":24,"correct":14},"D","质量回访",{"key":26,"text":27,"correct":14},"E","图纸会审","BC","施工质量的过程控制包括：施工准备、施工过程和施工验收等阶段的质量控制。其中，施工过程质量控制是指施工作业技术活动的投入与产出过程的质量控制，其内涵包括全过程施工生产及其中各分部分项工程的施工作业过程，过程质量控制是工程质量管理的重点。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]