[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983048":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983048,712,2,"多选题","勘察设计单位的利益诉求包括()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","业主的项目功能策划清晰",true,{"key":16,"text":17,"correct":14},"B","业主及时提供方案设计任务书及工程设计任务书",{"key":19,"text":20,"correct":14},"C","业主给予的设计周期充分，设计变更要求少、审批快",{"key":22,"text":23,"correct":24},"D","设计单位提供的图纸没有或极少有错误",false,{"key":26,"text":27,"correct":14},"E","及时支付设计费用","ABCE","勘察设计单位的利益诉求包括：①业主的项目功能策划清晰；②业主及时提供方案设计任务书及工程设计任务书；③业主给予的设计周期充分，设计变更要求少、审批快；④及时支付设计费用。D项，设计单位提供的图纸没有或极少有错误是施工单位的利益诉求。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]