[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983035":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983035,712,2,"多选题","编制项目进度计划的步骤有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","利用工作（工程）分解结构确定管理任务和子项任务",true,{"key":16,"text":17,"correct":18},"B","完成管理任务与子任务",false,{"key":20,"text":21,"correct":14},"C","检查工作之间的逻辑关系",{"key":23,"text":24,"correct":18},"D","确定工期",{"key":26,"text":27,"correct":14},"E","完善并优化进度计划","ACE","编制项目进度计划应掌握下列五个步骤的程序性工作方法：①利用工作（工程）分解结构确定管理任务和子项任务；②利用组织分解结构界定承担上述任务的机构与岗位；③检查工作之间的逻辑关系；④草拟进度计划；⑤完善并优化进度计划。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]