[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983034":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983034,712,2,"多选题","企业投资项目的备案程序包括()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","可行性研究",true,{"key":16,"text":17,"correct":14},"B","申报备案，申请相关材料",{"key":19,"text":20,"correct":14},"C","政府合规性审查",{"key":22,"text":23,"correct":24},"D","行业或部门规划",false,{"key":26,"text":27,"correct":14},"E","项目备案确认书","ABCE","企业投资项目的备案程序如图3-4所示。E项是政府投资项目审批决策程序的步骤。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]