[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983029":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983029,712,2,"多选题","关于盈亏平衡分析，下列说法错误的有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","根据其函数形式不同，盈亏平衡分析又分为线性盈亏平衡分析及非线性盈亏平衡分析",false,{"key":16,"text":17,"correct":14},"B","线性盈亏平衡分析是指项目的收入和成本都与产量之间呈线性关系",{"key":19,"text":20,"correct":21},"C","盈亏平衡生产能力利用率表示项目可以接受的最低产量",true,{"key":23,"text":24,"correct":21},"D","盈亏平衡分析能够揭示产生项目风险的原因",{"key":26,"text":27,"correct":14},"E","盈亏平衡分析的核心是确定盈亏平衡点","CD","C项，盈亏平衡产量表示项目可以接受的最低产量。低于此水平，项目就亏损。盈亏平衡生产能力利用率表示项目开始盈利的起点。D项，盈亏平衡分析虽然能够度量项目风险的大小，但是并不能揭示产生项目风险的原因。分析风险产生的根源，还需借助敏感性分析。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]