[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983027":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983027,712,2,"多选题","总价合同风险应对措施的实施要点包括()。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","采用合同手段",true,{"key":16,"text":17,"correct":14},"B","预先设立涨价预备金，应对涨价风险",{"key":19,"text":20,"correct":14},"C","当变更发生，双方可协商，对价格做适当调整，根据合同的工程量清单或暂定费对变更进行估价",{"key":22,"text":23,"correct":14},"D","要求承包商提供履约担保或者投保信用保险",{"key":25,"text":26,"correct":27},"E","规定工程量极限变动幅度，当工程量变幅超过极限幅度时，才允许适当调整单价来降低风险",false,"ABCD","总价合同风险应对措施的实施要点包括：①预先设立涨价预备金，应对涨价风险；②当变更发生，双方协商根据合同及工程量清单对变更进行估价；③要求承包商提供履约担保或者投保信用保险。E项是单价合同风险应对措施的实施要点。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]