[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983017":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983017,712,2,"多选题","业主在签订项目设计合同前，需要()。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","决定拟采用的项目管理模式",true,{"key":16,"text":17,"correct":14},"B","确定分专业工程的管理模式",{"key":19,"text":20,"correct":14},"C","确定各专业工程设计图的出图深度",{"key":22,"text":23,"correct":14},"D","确定相关专业工程招标所需达到的设计深度要求",{"key":25,"text":26,"correct":27},"E","确保提供的图纸没有或极少有错误",false,"ABCD","业主在签订项目设计合同前，需要决定拟采用的项目管理模式，以便确定相关专业工程招标所需达到的设计深度要求，还要确定分专业工程的管理模式，以便确定各专业工程设计图的出图深度。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]