[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983013":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983013,712,2,"多选题","由各参与方各自的项目管理集成的项目管理体系中，业主的核心工作包括()。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","确定项目的功能与规模，安排筹融资",true,{"key":16,"text":17,"correct":14},"B","建立项目管理体系与架构",{"key":19,"text":20,"correct":14},"C","决定其他各方参与项目的时间、方式和条件",{"key":22,"text":23,"correct":14},"D","制订项目管理的各项目标，并编制项目管理的全部预控计划",{"key":25,"text":26,"correct":27},"E","优先做好自己的管理工作",false,"ABCD","业主的项目管理工作具有独特的内容与要求，其核心工作包括确定项目的功能与规模，安排筹融资，建立项目管理体系与架构，决定其他各方参与项目的时间、方式和条件，制订项目管理的各项目标，并编制项目管理的全部预控计划等。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]