[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983011":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983011,712,2,"多选题","一般根据项目的类型及其产生的影响，环境影响评价的工作内容分为()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","建设条件调查",false,{"key":16,"text":17,"correct":18},"B","环境条件调查",true,{"key":20,"text":21,"correct":14},"C","项目分析",{"key":23,"text":24,"correct":18},"D","环境影响因素确定及分析",{"key":26,"text":27,"correct":18},"E","工程分析","BDE","工程建设项目环境影响评价的工作内容取决于项目对环境所产生的影响，一般根据项目的类型及其产生的影响分为五个部分：工程分析、环境条件调查、环境影响因素确定及分析、环境影响程度分析和环境保护措施。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]