[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983009":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983009,712,2,"多选题","在项目整体的进度管理体系及各个参与方承担的进度管理工作中，()所做的进度管理工作处于核心地位。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","业主",true,{"key":16,"text":17,"correct":14},"B","管理咨询单位",{"key":19,"text":20,"correct":21},"C","项目部经理",false,{"key":23,"text":24,"correct":21},"D","监理单位",{"key":26,"text":27,"correct":21},"E","施工方与设计方","AB","在项目整体的进度管理体系及各个参与方承担的进度管理工作中，业主及其聘用的管理咨询单位所做的进度管理工作无疑处于核心的地位。由于只有项目负责人才能全面掌握项目信息，而项目均是独一无二的，所以项目管理部经理在项目进度管理中仍占据核心地位与发挥核心作用。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]