[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983008":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983008,712,2,"多选题","施工准备阶段，施工单位应负责的活动包括()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","聘任项目经理",true,{"key":16,"text":17,"correct":14},"B","设立项目经理部",{"key":19,"text":20,"correct":21},"C","完成施工图纸的内部审查与外部审查",false,{"key":23,"text":24,"correct":14},"D","编制并完善施工组织设计及质量计划",{"key":26,"text":27,"correct":14},"E","施工现场准备","ABDE","在施工准备阶段施工单位应负责：①聘任项目经理，签署项目管理责任及授权书，实行项目经理责任制；②设立项目经理部，根据施工项目的规模、结构复杂程度、专业特点、人员素质、地域范围，确定项目经理部的组织形式及人员分配等；③编制并完善施工组织设计及质量计划；④编制施工项目管理规划及规章制度；⑤施工现场准备；⑥施工队伍的“人、料、机”到位；⑦编写开工申请报告，上报审批。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]