[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983005":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983005,712,2,"多选题","项目施工单位在不同的承包方式下，施工单位或工程总承包方介入的阶段各不相同。下列说法错误的有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","在国内施工总承包的方式下，施工单位在中标后照图施工，介入的是项目的施工阶段",false,{"key":16,"text":17,"correct":14},"B","在国外施工总承包方式下，施工单位介入了项目的施工图设计阶段",{"key":19,"text":20,"correct":21},"C","在国外施工总承包方式下，施工单位介入的是项目的施工阶段",true,{"key":23,"text":24,"correct":14},"D","在EPC工程总承包方式下，EPC工程总承包方介入的是项目建造的全过程",{"key":26,"text":27,"correct":21},"E","在EPC工程总承包方式下，EPC工程总承包方介入的是项目的施工阶段","CE","在国内施工总承包、国外施工总承包和EPC\u002FP&D+B工程总承包三种方式下，施工单位介入的阶段分别是：①在国内施工总承包方式下，项目业主以施工图纸作为招标图纸，施工方在中标后照图施工，介入的只是项目的施工阶段；②在国外施工总承包方式下，业主以相当于初步设计或扩大初步设计的图纸招标，施工单位在中标并签约后需自己出施工图并向监理报批，而后再照图施工，施工单位就已介入了项目的施工图设计阶段；③在工程总承包(EPC\u002FP&D+B)方式下，EPC工程总承包方所介入的是项目建造期的全过程。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]