[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-983004":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},983004,712,2,"多选题","关于工程建设项目管理实施方法的说法，正确的有（)。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","采用快速路径法可使项目工期更短",true,{"key":16,"text":17,"correct":18},"B","快速路径法相对于线性顺序法更先进",false,{"key":20,"text":21,"correct":14},"C","采用线性顺序法可使项目风险更小",{"key":23,"text":24,"correct":14},"D","同一个项目中可同时采用线性顺序法和快速路径法",{"key":26,"text":27,"correct":14},"E","快速路径法应以线性顺序法为基础","ACDE","B项，线性顺序法与快速路径法本身并无先进与落后之分，它们只是分别适用于不同技术复杂程度与管理风险要求的项目。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]