[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982992":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982992,712,2,"多选题","某工程采用暂估工程量固定单价合同，在施工阶段，导致业主方合同价格风险的主要因素有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","施工安全措施不当",false,{"key":16,"text":17,"correct":14},"B","市场物价起伏",{"key":19,"text":20,"correct":21},"C","工程量无法准确计算",true,{"key":23,"text":24,"correct":21},"D","清单中项目特征描述不明确",{"key":26,"text":27,"correct":14},"E","市场人工费上涨","CD","工程项目施工阶段，业主面临的合同风险包括外部环境因素变化产生的风险、工程变更风险、工程质量风险等。其中估量工程量单价合同的风险因素主要有：①不能准确地计算工程量；②清单中的项目不明确。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]